A basic note on throughput accounting – for advanced management accounting students
Highlight 5 main ideas of throughput
accounting and provide a simple calculation example on throughput accounting.
Throughput accounting (TA) is a short-term
decision-making approach that focuses on maximizing cash generated through
sales while managing the resource that limits the whole operation—the
bottleneck. It is closely linked to the Theory of Constraints.
Five
main ideas
1. Throughput
is the key measure of value.
Throughput is sales revenue minus totally variable costs, usually direct
material costs:
Throughput=Sales revenue−Direct material cost
It counts
only when goods are actually sold, not merely produced.
2. Most
other operating costs are treated as fixed in the short run.
Labor, rent, utilities, depreciation, and overheads are grouped as total
factory costs or operating expenses; TA generally does not allocate them to
individual products.
3. The
bottleneck determines system output.
The constraint is the scarce resource—such as a machine, skilled worker, or
process—that limits total production and sales. An hour lost at the bottleneck
is an hour lost for the entire system.
4. Products
should be ranked by throughput per unit of bottleneck time.
Rather than choosing the product with the highest profit per unit, TA
prioritizes the product that generates the most throughput per hour or minute
of constrained resource.
5. Improvement
follows the five focusing steps.
Identify the bottleneck, exploit it fully, subordinate other activities to it,
elevate or expand it if needed, and repeat once a new bottleneck emerges.
Simple
calculation example
A company makes two products using one bottleneck
machine with 1,000 machine hours available per month.
|
Item |
Product A |
Product B |
|
Selling price per unit |
$100 |
$80 |
|
Direct material cost per unit |
$40 |
$20 |
|
Throughput per unit |
$60 |
$60 |
|
Bottleneck hours per unit |
2 |
1 |
|
Maximum monthly demand |
300 units |
800 units |
Step
1: Calculate throughput per unit
Product A=100−40=$60
Product B=80−20=$60
Both products have the same throughput per unit.
Step
2: Calculate throughput per bottleneck hour
Product A=602=$30 per bottleneck hour
Product B=601=$60 per bottleneck hour
Product B is more valuable because it creates twice
as much throughput from each scarce machine hour.
Step
3: Rank and allocate bottleneck time
Produce Product B first, up to its demand:
800 units×1 hour=800
Remaining bottleneck hours:
1,000−800=200 hours
Use the remaining time for Product A:
200÷2=100 units of Product A
Step
4: Calculate total throughput
Product B=800×60=$48,000
Product A=100×60=$6,000
Total throughput=$54,000
If total factory costs are $30,000 per month,
profit is:
$54,000−$30,000=$24,000
The key insight is that Product B should be
prioritized despite having the same per-unit throughput, because it uses the
bottleneck more efficiently.